Five key things have happened since our last report.

The first is the removal of some Japanese Knotweed from a patch of land on the site.  This invasive plant was introduced to the UK in the late 1800s and can create a whole range of problems.

The second is what is known as a ‘soft strip’ in the former Central Library. A ‘soft strip’ involves the removal of internal fixtures and fittings, ultimately leaving a ‘frame’ ready for building and construction work. Carpet tiles have been taken up, windows, doors and door frames have been removed. You can get a good idea of the work that’s been undertaken from this image, which shows a part of the Library which is scheduled for demolition.

A photograph of part of Plymouth's Central Library ready for demolitition
This part of the former Central Library building has been prepped ready for demolition. Image taken by Penny Cross, Plymouth Herald

The third is the appearance of another set of hoardings – this time at the back of Chapel Lane – shown here on a lovely sunny day slightly earlier in the month.

Hoardings on Chapel Lane, Plymouth as part of the History Centre construction site
New hoardings at the back of the History Centre site

The fourth is the demolition of some small outbuildings in the car park next to St Luke’s Church. This work largely took place during the weeks of 6 March and 13 March. The demolition will enable us to create a walkway from Chapel Street through to Tavistock Place, providing easy access to the History Centre complex and the public piazza.

Demolition work begins at the Plymouth History Centre site - 10 March 2017
Demolition work begins. This shot was taken on 10 March 2017 from Chapel Lane
Demolition work at the Plymouth History Centre site - 28 March 2017
The demolition of one of the St Luke’s Church outbuildings complete. This shot was taken on 28 March 2017 from Tavistock Place

The fifth and probably most publicly visible piece of work is the scaffolding. This started to go up on 20 March and, due to its extent, will take around five weeks to install.

Scaffolding on the former Plymouth Central Library building - March 2017
Scaffolding has started to go up on the former Central Library building

A temporary roof has also been put up over the former Central Library building. The existing roof will be taken off and a new one put on. This work will take place under the temporary roof meaning the rest of the building will be kept dry.

The temporary roof on the former Plymouth Central Library building - March 2017
A new roof will be created under the temporary one now in place over the former Central Library building. Image taken by Penny Cross, Plymouth Herald

We’ll be back with another #BuildUpdate in late April when there will no doubt be lots more work to report on. We’ll finish with our latest progress report video which gives you an overview of a number of things that have been achieved for the History Centre from January to March 2017.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s